Westside Drive Area Utility Improvement Project
The Town is currently working with Underwood Engineers, Inc. to develop a plan for municipal infrastructure improvements within the Westside Drive Neighborhood. This work is part of the Town’s ongoing work to provide reliable utility services to residents and is also recommended by the Town’s sewer system Combined Sewer Overflow (CSO) Long Term Control Plan with EPA.

Status Updates
4/3/2026: Drain installation continues on Westside Drive and Laperle Ave during the next two weeks. The temporary paving schedule will be adjusted to align with inclement weather forecasts. See attached weekly work zone document for details.
3/27/2026: Drain installation continues on Westside Drive and Blanche Lane during the next two weeks. The temporary paving schedule will be adjusted to align with inclement weather forecasts. See attached weekly work zone document for details.
3/12/26-3/20/2026: Drain installation continues on Westside Drive and Scamman Lane during the next two weeks. The temporary paving schedule will be adjusted to align with inclement weather forecasts. See attached weekly work zone document for details.