Linden Street Bridge Project
Linden Street bridge is scheduled to re-open to traffic on November 13. The contractor, George R. Cairns & Sons, will continue to be working on project completion activities until that time including water main re-connection, sidewalks, paving, guardrails, and pavement striping.
Project Information:
The Linden Street Bridge project began on July 6th and is expected to continue through October 2015. The project involves removing the existing culverts and replacing them with a concrete bridge. The contractor, George R. Cairns & Sons, will be setting up equipment and materials at the site over the next 2 weeks. They anticipate beginning demolition of the culverts on Monday, July 20th, which means that the bridge will then be closed to all traffic until the end of October. Traffic will be detoured via Pine St, Court St and Gary Lane.
For Questions:
Contact Jen Mates (418-6431) or Jay Perkins (773-6163)
Click any thumbnail image to view a slideshow